Home > NLS Digital Transition > Network Digital Planning - Module 2: Application

NLS: That All May Read

Network Digital Planning - Module 2: Application (Whittall)

Revised: 12/31/08-rev 10

Revise and update NLS individual application twice–first for the interim and then for the new digital program. This includes revising the factsheet on playback machines to delete record player for the interim, and another revision of the factsheet to reflect the availability of digital talking-book machines and to accompany the new digital program individual application. If it is determined to be necessary, the interim individual application/factsheet should be translated into Spanish. The digital program's individual application and digital factsheet on playback machines will be translated into Spanish. Work with PMS on the content revisions, translations, and printing. PMS has requested that we sequence the application production to work on one product at a time.

2007

 
11/07 Determine if the current application needs to be reprinted before the end of 2008. Reference requested printing of application (as of 10/4/07, there were 53,600 applications for individuals. These are being used at a rate of 7,875 per month. This stock of applications is expected to last until May 2008). [Completed 10/07]
11/30/07 Discuss with PMS the possible need for an interim application and the publication of the revised digital application. Establish a projected distribution date for the new NLS digital application. [Completed 10/07]
12/07 Request printing of interim individual application as a substitute for reprinting current application and prepare and revise the factsheet to go with it. [Complete 12/07]

2008

 
1/14/08 Draft interim application for digital program. [Completed 1/22/08]
1/23-31/08 Circulate draft interim individual application/factsheet for five-day review. [Completed 2/6/08-2/11/08]
2/4/08 Circulate interim individual application/factsheet second draft for five-day review. [Completed 2/21/08-2/27/08]
3/1/08 Submit revised interim individual application/factsheet to PMS for printing. [Completed 1st 2/13/08]
3/15/08 Submit approved interim individual application/factsheet to Digital Transition Advisory Committee (DTAC) through the listserv. [Completed 3/28/08]
3/28/08 Discuss institutional policy with DTAC including discussion of the application (CRO). [Completed 3/28/08]
4/15/08 Confirm if a Spanish translation of interim application/factsheet is needed. If so request a Spanish translation of the English version from PMS. [Completed 2/20/08]
4/4/-5/1/08 Resubmitted revise interim individual application/factsheet. Print and prepare for distribution. [Completed 4/3/08]
5/1/08 The revise interim individual application/factsheet was approved be the Director and sent out for design approval. [Completed 5/1/08]
5/14/08 When the revised Interim individual application/factsheet returns from design approval have it translated into Spanish. [Completed 6/2/08]
7/25/08 Determine if interim Spanish application/factsheet is needed and identify quantity for printing. [9/30/08 out for Spanish review before printing]
7/25/08 Post revised interim application/factsheet in English and Spanish on the NLS web site.
8/15/08 Circulate draft of digital individual application/factsheet to include new digital player for five-day review. [Completed 9/4/08]
9/30/08 Submit draft of digital individual application/factsheet for digital program to PMS. [Completed 9/14/08 returned and back to PMS 10/2/08, up dated circulated to Kurt , Carolyn S, Michael K,11/2/08, returned from PMS 11/17/08] Share the draft with DTAC on the Listserv
9/30/08 Submit revised individual digital application/factsheet to PMS for printing (Reference Section). [Completed 9/14/08 returned and back to PMS 10/2/08]
10/08 Identify quantity for printing application for digital individual application/factsheet. Ensure Reference Section includes printing request in FY09 printing plan for budget.
11/08 Print interim Spanish application and prepare for distribution. [Out for final Spanish review]
11/30/08 Distribute interim Spanish application. [10/29/08 ,1,000 ordered]

2009

 
1/09 Print revised individual digital application/factsheet and prepare for distribution. In PMS 1/6/09 format review.
1/09 Ensure that the new digital applications/factsheet is translated into Spanish
2/30/09 Distribute digital NLS individual applications.
2/30/09 Post two revised applications on the NLS web site.
3/09 Prepare Spanish versions of the digital individual and institutional applications for distribution
4/09 Explore electronic storage of application data and use of electronic signatures

Back to Table of Contents


Library of Congress Home    NLS Home    Comments about NLS to nls@loc.gov

About this site    Comments about this site to nlswebmaster@loc.gov

Posted on 2009-02-20