Produce new images featuring DTBM

 
8/1/07 10/1/07 Procure photography services Completed  
10/15/07 3/8/08 Schedule six photo sessions Completed  
3/28/08 3/28/08 Select and submit photographs for approval. Completed
3 of 6 approved
 
4/2/08 4/30/08 Secure new photography contract Completed  
8/5/08 8/5/08 Schedule additional photo sessions (DTBM alone/and w/patrons) Photographer rejected Cancelled  
8/5/08 8/28/08 New photographer being sought Completed  
8/5/08 8/8/08 Research product photographers and request samples of work Completed  
8/12/08 8/28/08 Receive work samples and select candidates Completed  
8/28/08 8/28/08 Request proposals from candidates Completed  
10/1/08 10/15/08 Receive proposals and select photographers; Process Momentum requisitions. Completed  
10/20/09 11/5/08 Receive contracts and brief photographers on project Completed  
11/6/08 1/16/09 Schedule photography sessions, review and approve images and receive image files Completed  
2/9/09 6/8/09 Produce 6 new photomurals In process  
3/2/09 3/15/09 Make images available for download on web site In process  
3/9/09 4/30/09 Design and approve 2008-2010 Poster Series Images In process  
5/1/09 6/30/09 Produce 1st poster and distribute to warehouses ¹    

Start

Finish

Project and Tasks

Status

Dependency

   

Upgrade desktop publishing templates to accept DBs

 
4/1/08 4/1/08 PMS and Automation meet with vendor to discuss scope of work Completed  
2/8/08 7/30/08 Procure software services for desktop publishing templates Completed 7/24  
5/21/08 5/21/08 Justification for BAE correcting XML files submitted Completed  
4/1/08 7/30/08 Automation prepares specification for templates
  • XML specifications revised and new document created to eliminate flaws
Completed  
6/15/08 7/30/08 Design and approve page mock ups for TBT and DTB+ announcements Completed Approved 7/28  
11/13/08 11/20/08 Mock pages revised Completed  
11/20/08 1/29/09 Vendor review mock pages; awaiting XML spec from NLS Completed Pending completion of PICS2
11/20/08 1/28/08 Automation updates current specifications to accommodate DB announcements In process Installation of new PICS
1/29/09 2/19/09 Vendor analyzes template requirements; develops and delivers templates Completed  
2/20/09 3/20/09 PMS and Automation test templates In process  
3/23/09 4/3/09 Vendor adjusts templates as needed    
4/6/09 4/17/09 PMS and Automation test and approve templates   Test data available in PICS

Start

Finish

Project and Tasks

Status

Dependency

   

Announce availability of DBs

 
   

A. Magazines and catalogs

 
5/4/08 5/4/08 Announce renaming of Cassette Books catalog to Digital Talking Books Plus (DTB+) Completed  
6/23/08 8/30/08

Design and approve new covers for TBT and DTB+
Approved 8/6/08

Completed  
1/7/09 1/7/09 Receive PDFs and native files of cover designs Completed  
4/1/09 4/30/09 Notify network of publication changes    
5/18/09 5/18/09 Extract booklist from PICS for Talking Book Topics July-August 09   Availability of DBs
5/18/09 5/18/09 Extract TBT list for Braille Book Review July-August 09   As above
8/1/09 8/1/09 Release Talking Books Topics July-August 09 (print and cassette)   As above
3/2/09 3/13/09 Release Talking Book Topics March-April 09   As above
8/1/09 8/1/09 Release Braille Book Review (w/TBT order forms) July-August 09    
11/15/09 1/30/10 Acquire ISSN from LC ISSN Center    
1/15/10 1/30/10 Extract booklist from PICS for Digital Talking Books Plus (annual recorded books catalog)   As above
5/3/10 5/15/10 Release Digital Talking Books Plus Catalog   As above

Start

Finish

Project and Tasks

Status

Dependency

   

B. DB Sampler

 
6/9/08 6/9/08 Receive approved DB sampler from CDS Completed  
6/19/08 6/19/08 Returned for corrections Completed  
7/25/08 9/30/08

Receive final manuscript, layout, and approve

  • Partial manuscript in house; Introduction and contents needed
Completed  
1/12/09 3/30/09 Print and distribute to libraries and NLS warehouse In process  
1/12/09 1/23/09 Develop scope of work and request bids for braille and recorded copies Completed  
2/6/09 3/30/09 Produce braille copies In process  
2/13/09 3/30/09 Produce recorded copies In process  

Start

Finish

Project and Tasks

Status

Dependency

   

Applications

 
   

A. Application—Individual

 
4/28/08 5/2/08 Review and approval of individual application Completed  
5/15/08 5/29/08 Designed, reviewed, and approved; receive PDF Completed  
6/12/08 9/19/08 Print and distribute individual application to warehouses Completed

(Encountered and resolved problems with printer)

   

B. Application—Spanish

 
7/28/08 7/28/08 Manuscript received Completed  
8/14/08 11/18/08 Layout, review, and approve Completed  
11/26/08 1/7/09 Print and distribute to warehouses Completed  
   

C. Application—Digital

 
11/20/08 12/5/09 Manuscript received Completed  
12/5/08 2/20/09 Layout, review, and approve Approved  
3/1/09 3/15/09 Print and distribute to warehouses In process  

 

 

C. Application—Digital (Spanish)

 
TBD   Manuscript received    
TBD   Layout, review, and approve    
TBD   Print and distribute to warehouses    

¹ Posters will be produced in six-month intervals

Back to Table of Contents


Library of Congress Home    NLS Home    Comments about NLS to nls@loc.gov

About this site    Comments about this site to nlswebmaster@loc.gov

Posted on 2009-05-13