Project and Tasks
Status
Dependency
Produce new images featuring DTBM
8/1/07 10/1/07 Procure photography services Completed 10/15/07 3/8/08 Schedule six photo sessions Completed 3/28/08 3/28/08 Select and submit photographs for approval. Completed
3 of 6 approved4/2/08 4/30/08 Secure new photography contract Completed 8/5/08 8/5/08 Schedule additional photo sessions (DTBM alone/and w/patrons) Photographer rejected Cancelled 8/5/08 8/28/08 New photographer being sought Completed 8/5/08 8/8/08 Research product photographers and request samples of work Completed 8/12/08 8/28/08 Receive work samples and select candidates Completed 8/28/08 8/28/08 Request proposals from candidates Completed 10/1/08 10/15/08 Receive proposals and select photographers; Process Momentum requisitions. Completed 10/20/09 11/5/08 Receive contracts and brief photographers on project Completed 11/6/08 1/16/09 Schedule photography sessions, review and approve images and receive image files Completed 2/9/09 6/8/09 Produce 6 new photomurals In process 3/2/09 3/15/09 Make images available for download on web site In process 3/9/09 4/30/09 Design and approve 2008-2010 Poster Series Images In process 5/1/09 6/30/09 Produce 1st poster and distribute to warehouses ¹ Start
Finish
Project and Tasks
Status
Dependency
Upgrade desktop publishing templates to accept DBs
4/1/08 4/1/08 PMS and Automation meet with vendor to discuss scope of work Completed 2/8/08 7/30/08 Procure software services for desktop publishing templates Completed 7/24 5/21/08 5/21/08 Justification for BAE correcting XML files submitted Completed 4/1/08 7/30/08 Automation prepares specification for templates
- XML specifications revised and new document created to eliminate flaws
Completed 6/15/08 7/30/08 Design and approve page mock ups for TBT and DTB+ announcements Completed Approved 7/28 11/13/08 11/20/08 Mock pages revised Completed 11/20/08 1/29/09 Vendor review mock pages; awaiting XML spec from NLS Completed Pending completion of PICS2 11/20/08 1/28/08 Automation updates current specifications to accommodate DB announcements In process Installation of new PICS 1/29/09 2/19/09 Vendor analyzes template requirements; develops and delivers templates Completed 2/20/09 3/20/09 PMS and Automation test templates In process 3/23/09 4/3/09 Vendor adjusts templates as needed 4/6/09 4/17/09 PMS and Automation test and approve templates Test data available in PICS Start
Finish
Project and Tasks
Status
Dependency
Announce availability of DBs
A. Magazines and catalogs
5/4/08 5/4/08 Announce renaming of Cassette Books catalog to Digital Talking Books Plus (DTB+) Completed 6/23/08 8/30/08 Design and approve new covers for TBT and DTB+
Approved 8/6/08Completed 1/7/09 1/7/09 Receive PDFs and native files of cover designs Completed 4/1/09 4/30/09 Notify network of publication changes 5/18/09 5/18/09 Extract booklist from PICS for Talking Book Topics July-August 09 Availability of DBs 5/18/09 5/18/09 Extract TBT list for Braille Book Review July-August 09 As above 8/1/09 8/1/09 Release Talking Books Topics July-August 09 (print and cassette) As above 3/2/09 3/13/09 Release Talking Book Topics March-April 09 As above 8/1/09 8/1/09 Release Braille Book Review (w/TBT order forms) July-August 09 11/15/09 1/30/10 Acquire ISSN from LC ISSN Center 1/15/10 1/30/10 Extract booklist from PICS for Digital Talking Books Plus (annual recorded books catalog) As above 5/3/10 5/15/10 Release Digital Talking Books Plus Catalog As above Start
Finish
Project and Tasks
Status
Dependency
B. DB Sampler
6/9/08 6/9/08 Receive approved DB sampler from CDS Completed 6/19/08 6/19/08 Returned for corrections Completed 7/25/08 9/30/08 Receive final manuscript, layout, and approve
- Partial manuscript in house; Introduction and contents needed
Completed 1/12/09 3/30/09 Print and distribute to libraries and NLS warehouse In process 1/12/09 1/23/09 Develop scope of work and request bids for braille and recorded copies Completed 2/6/09 3/30/09 Produce braille copies In process 2/13/09 3/30/09 Produce recorded copies In process Start
Finish
Project and Tasks
Status
Dependency
Applications
A. Application—Individual
4/28/08 5/2/08 Review and approval of individual application Completed 5/15/08 5/29/08 Designed, reviewed, and approved; receive PDF Completed 6/12/08 9/19/08 Print and distribute individual application to warehouses Completed (Encountered and resolved problems with printer)
B. Application—Spanish
7/28/08 7/28/08 Manuscript received Completed 8/14/08 11/18/08 Layout, review, and approve Completed 11/26/08 1/7/09 Print and distribute to warehouses Completed C. Application—Digital
11/20/08 12/5/09 Manuscript received Completed 12/5/08 2/20/09 Layout, review, and approve Approved 3/1/09 3/15/09 Print and distribute to warehouses In process
C. Application—Digital (Spanish)
TBD Manuscript received TBD Layout, review, and approve TBD Print and distribute to warehouses
¹ Posters will be produced in six-month intervals